Vineyard Park Sports Courts Construction Work Starts July 9, 2018

Post Date:07/05/2018
MEDIA RELEASE

FOR IMMEDIATE RELEASE

Date: July 5, 2018

Contact: Joe Tagliaboschi, Public Works Director
                jtagliaboschi@yville.com (707) 944-8851

Subject: Vineyard Park Sports Courts Construction Work Starts July 9, 2018

The Sports Courts Improvement Plan at Vineyard Park will begin construction on July 9, 2018. The project which received broad support from the community and approved by the Council will utilize the existing courts to create one dedicated Tennis Court and four dedicated Pickleball Courts. The new courts will provide a resilient surface which is gentle on the players’ joints and drainage improvements to give a more playable and longer lasting surface.

All work will be done between 9:00 a.m. to 5:00 p.m. to adhere to the Town’s noise and construction policy. Construction activity will be broken down into four phases:

• Phase I: Removal of current courts starting July 9.
• Phase II: 30 day cure time for the concrete pour that is scheduled for mid-August.
• Phase III: Courts playing surface installations around mid-September.
• Phase IV: Project completion by October.

We apologize for any inconvenience while the Sports Courts are closed for renovation. Please, be sure to check the new installed Outdoor Exercise Equipment at Vineyard Park.